The applicable and effective task
With the diagnosis in hand, Framework B decides what to do — in the RCM order of preference (SAE JA1011; Moubray, RCM II). A task only enters the plan if it is technically APPLICABLE (detects or prevents that failure mode) and WORTH DOING (costs less than the consequence it avoids).
The task hierarchy
- 1CBM
On-condition — if the failure gives a measurable warning (P-F interval), monitor the condition and act on the signal. Inspection ≤ P-F/2.
- 2TBM
Scheduled restoration/discard — only when a defined wear-out zone exists (β > 1 with predictable age). Interval before the wear zone.
- 3Proof Test
Failure-finding — for HIDDEN functions (protections, redundancies): tests the function at the interval (FFI) dictated by the required availability.
- 4RTF
Run to failure — legitimate when nothing above applies and the consequence is economic only.
- 5Redesign
Redesign — compulsory when the consequence is safety/environmental and no task reduces the risk to a tolerable level.
Consequence as the filter
The same technical failure changes strategy with its consequence: safety/environmental demands proven risk reduction (or redesign); operational weighs downtime cost; non-operational weighs repair cost only. That is why the selector asks about consequence before closing the decision.